Karnataka RERA Extends Real Estate Projects Deadline by Three Months
April 8, 2020: As the supply chain for construction material has been disrupted across the country due to lockdown the Karnataka Real Estate Regulatory Authority (RERA) has given an extension on completion deadline to all residential buildings across Bengaluru. The MahaRERA had also extended timelines for completion of projects for 3 months.
Apart from disruption in supply of construction material, a majority of labour workforce has also migrated back to their home-towns. Given that the current circumstances are not conducive to the construction work.
The Karnataka RERA authority has extended project deadlines by 3 months for all RERA registered projects whose completion date (including revised completion date) expires on or after 15 March 2020.
The time limit of all statutory compliances in accordance with the Real Estate (Regulation and Development) Act 2016 and the rules and regulations which were due in March, April and May 2020 has been extended till 30 June 2020.
Check Out homes for rent or sale or buy at nobroker with zero brokerage. Just click below to found out more.

Most Viewed Articles
GFRG Panels: A New Technology in Building Construction
January 31, 2025
261925+ views
February 6, 2026
232021+ views
Top Cleanest Cities in India: Swachh Survekshan Top Ranked List
July 25, 2025
227542+ views
How Mivan Construction Technology Is Transforming the Art of Building!
January 31, 2025
186212+ views
CIDCO Lottery: Application Process, Eligibility, Flat Prices and Dates in 2026
April 30, 2025
141813+ views
Loved what you read? Share it with others!
Recent blogs in
Plots Under 10 Lakhs in Bangalore in 2026
June 4, 2026 by Kruthi
Full RM + FRM support
Join the conversation!